PROJECT UPDATES
There's always something happening at Johnson Ranch — see the status of various projects the Association is working on around the community right here.
Saddle Park Playground
Wall Project
April 2020 - December 2022
 
Back in 2020, Finesse Construction came out and inspected all the walls the HOA is responsible for maintaining and created a report for which walls needed to be repaired. This project was laid out in four phases, The 4th Phase will be beginning the week of October 10th, because there were some delays due to summer storms.
 
The current wall project is only to fix what was reported back when they initially walked the property — we understand there has been further deterioration since then. When phase four is complete, the wall project will be concluded. We will still be addressing any issues with walls that fall under the Association's responsibility that need to be corrected on a case-by-case basis.
 
Last Updated - September 27th, 2022
Stonegate Roadwork
Stonegate Roadwork
October 2022
 
All the roads in Stonegate will be crack-filled, and then the asphalt will be re-coated. The crack seal will begin on October 3 and will most likely take all week, but it should not affect any traffic other than going around the crew as they move through the community.
 
The seal coating will begin the week of October 10 and will be completed in four phases. During each phase, the portion of the roads worked on will be closed. Residents and visitors cannot drive on the streets being worked on for 24 hours from the time work begins. They may instead park on streets in other portions of the neighborhood that are not being worked on or in the Golf Club parking lot.
 
More info and closure map
 
If you have any questions, please call our office during regular business hours at 480-987-8073.
 
Last Updated October 3, 2022.
Pond Dredging and Restocking
October 2022
 
The pond will be dredged to clean out all debris and sediment and remove all the dead algae. This will be taking place the week of October 3rd and the pond will be closed throughout this process.
 
Once the lake is cleaned out and refilled, it will be restocked with fish.
 
Last Updated - September 27th, 2022
Grass Over Seeding
October 2022
 
The landscaping crew will be starting the over seeding process, in some areas they have already started preparing the grass for this by cutting it down very low.
 
The only areas that will be over seeded will be in and around the pool areas and the Pitch and Putt.
 
Over the next few weeks the sprinklers will be run a few more times than usual through out the day in these areas so if you see them on in the morning and then again in the afternoon this is regular and not a malfunction.
 
Once they over seed the Pitch and Putt it will be closed for 10 days, we will send out notifications when that happens.
 
Last Updated - October 3rd, 2022