PROJECT UPDATES
There's always something happening at Johnson Ranch — see the status of various projects the Association is working on around the community right here.
Saddle Park Playground
Wall Project
Ongoing
 
The original wall project is completed, we are moving forward now with quarterly inspections of different zones to make sure we keep on the walls to stop such a large project being needed again.
Last Updated - November 21st, 2023
Pool Tile repairs
2024
 
Above and Beyond Pools began this project on January 8th; they started with Indigo Pool; they have removed all the tiles and will begin laying the new tiles on the weekend of January 13th; after they finish with Indigo, they will move on Lakeview Pool and then Stardust after that. Repairs at Indigo Sky Pool were completed as of Friday, February 2. 
 
Lakeview Pool is closed as of Monday, February 5. The pool is currently being drained so that tile repair can begin.

 
Last Updated - February 7, 2024
Pickleball Courts
2024
We are awaiting permits from the county.

 
Last Updated - November 21st, 2023
Pitch and Putt Walking Path
2023
 
Caretaker has begun carving out the area for the walking path and will begin the concrete border in the next couple weeks, there have been some issues along the path with drainage, Caretaker is working on this issue now and should be complete in the next 2 weeks.
 
Last Updated - January 11th, 2024
 
 
Completed Projects
 
Pond Dredging- This project was completed in October 2022. The water was emptied and the majority of the algae was pushed towards the pumps and removed from the bottom of the pond.
 
Stonegate Road Reseal- This project was completed in October 2022. Holbrook asphalt completed crack sealing and resealed the entire roadway and also the pool parking lots.
 
Pond Restocking - The pond was restocked with Bluegill, Redear, Speckle belly, Large mouth Bass, and Channel Catfish in October 2023.
 
Grass Overseeding - The Pitch and Putt and grass areas around the pools were over seeded in October 2023.
 
Pool Tile Replacement - The maintenance team replaced the falling off tile at the pools in December 2022
 
Johnson Ranch Monument - The monument is now being lit by solar lights. February 2023.
 
Cactus Park Update - New workout equipment and a spinning feature have been placed at Cactus Park. February 2023.
 
Dry Well Cleaning - The dry well cleaning has been completed for this year,  11 dry-wells and 8 head-walls were cleaned, this will help the storm water drain quicker and not build up in areas. February 2023.
 
Storm Wall Damage - Evolution Construction completed the repairs on 16 walls around property that were caused by falling trees and heavy winds during a storm in September of 2022. April 2023
 
Pool Filter Media Change - Above and Beyond Pools removed all the old sand and put new sand in all the filters at all 3 pools, this should be done every 2-3 years at it makes it easier to keep the pools clean and maintain the chemical levels in an optimum range while using less chemicals.
 
Stonegate Road Repairs- Holbrook came back out in June of 2023 to complete warranty work and seal a couple areas that were missed.
 
Wall Project- Finesse has completed all but a couple walls that were missed which they are finishing up on now September 2023.
 
 
Last Updated - November 21st, 2023