PROJECT UPDATES
There's always something happening at Johnson Ranch — see the status of various projects the Association is working on around the community right here.
Saddle Park Playground
Wall Project
April 2020 - December 2022
 
Back in 2020, Finesse Construction came out and inspected all the walls the HOA is responsible for maintaining and created a report for which walls needed to be repaired. This project was laid out in four phases, The 4th Phase is currently in progress and should be completed around the beginning of the new year. ( This project is still underway but has been delayed a couple weeks due to material delays and also all the rain we have received over the last few weeks).
 
The current wall project is only to fix what was reported back when they initially walked the property — we understand there has been further deterioration since then. When phase four is complete, the wall project will be concluded. We will still be addressing any issues with walls that fall under the Association's responsibility that need to be corrected on a case-by-case basis.
 
Last Updated - November 19th, 2023
Johnson Ranch Monument
January 2023
 
The Monument sign on Hunt Highway on the East side of the road just north of Solera has lost power, we are looking into changing over to a solar light to avoid having to dig up conduit to find the break.
 
Last Updated - January 19th 2023
Storm Wall Damage
2023
 
During the Monsoon season of 2022 we had several areas of wall damaged by falling trees. We have created an RFP for these repairs and sent them out to several Contractors.
 
We Currently have 1 bid and should be getting another by the end of the week to take to next weeks Board of Directors Meeting.
 
Last Updated - January 19th, 2023
Cactus Park Maintenance
February 2023
 
We will be adding workout equipment to the Cactus Park area and one play item for kids which is a spinning orb.
 
Play It Safe Playgrounds will be adding the equipment starting January 31 - February 3rd.
 
Last Updated - January 30th, 2023
Dry Well Cleaning
February 6th-14th 2023
 
Around the property we have several Dry Wells that collect the excess water during storms to prevent areas from flooding and avoid water erosion. Once a year we have these dry wells assessed to see if they need to be cleaned or repaired.
in December we had Storm Water Pros LLC complete this assessments, there findings and proposal for cleaning was presented to the Board of Directors at the January Board Meeting and the Board approved the proposal.
 
On February 6th Storm Water Pros LLC will be onsite to clean out several of these Dry Wells which they deemed necessary to cleaned, there should be no impact to residents during this process but there will be large vehicles, like the one in the picture, around the property completing the maintenance. This process will take about 9 days.
 
 
 
Last Updated - January 30th, 2023
Completed Projects
 
Pond Dredging- This project was completed in October 2022. The water was emptied and the majority of the algae was pushed towards the pumps and removed from the bottom of the pond.
 
Stonegate Road Reseal- This project was completed in October 2022. Holbrook asphalt completed crack sealing and resealed the entire roadway and also the pool parking lots.
 
Pond Restocking - The pond was restocked with Bluegill, Redear, Speckle belly, Largemouth Bass, and Channel Catfish in November 2022.
 
Grass Overseeding - The Pitch and Putt and grass areas around the pools were overseeded in November 2022.
 
Pool Tile Replacement - The maintenance team replaced the falling off tile at the pools in December 2022
 
Last Updated - January 19th, 2023